Programme at a glance
Provenance and settlement infrastructure for battery materials, delivered to the ECB under the Appia programme, with the CRRC EU Battery Passport flow as the first live pilot.
12
Work packages
18
Planned roles
27 months
Oct 2026 to Dec 2028
200M/day
Transaction design capacity
3
Delivery entities
What is being built
Four capabilities, delivered as one platform.
- Track, trace, provenance
- Asset onboarding, a ten-stage lifecycle metadata schema and a provenance chain that survives audit. This is the foundation everything else sits on.
- Passport compliance
- Token metadata and lifecycle data mapped to EU Battery Regulation 2023/1542 and Digital Product Passport requirements, aligned to Catena-X and CIRPASS.
- Settlement
- Programmable delivery-versus-payment with conditional compliance verification, interoperating with TARGET Services over ISO 20022.
- Quantum-resistant security
- CRYSTALS-Kyber and CRYSTALS-Dilithium primitives with HSM-backed key management, designed to coexist with Eurosystem cryptographic standards.
Milestone spine
Contractual dates. Amber marks the four points where slippage moves the end date.
MC
31 Aug 2026
Contract suite executed
Mob
1 Oct 2026
Formal mobilisation
M0
31 Dec 2026
Statement of work signed off
M1
31 Mar 2027
Architecture baseline frozen: schema, API, ISO 20022 catalogue, passport schema, cryptographic coexistence, SLA values
M2
30 Jun 2027
Integration scaffold and engine core operational
M3
15 Dec 2027
First end-to-end issuance, compliance gateway live
M4
30 Jun 2028
Interoperability with TARGET Services demonstrated
M5
1 Sep 2028
Security audit closed, documentation final, code freeze
M6
1 Oct 2028
Knowledge transfer complete, test entry
M7
31 Oct 2028
System integration testing complete
M8
30 Nov 2028
User acceptance and CRRC pilot complete
M9
31 Dec 2028
Final test report and go/no-go recommendation
Phasing
| Phase | Window | What has to be true at the end |
|---|---|---|
| Phase 0 | Oct 2026 – Mar 2027 | Architecture baseline workshop held and the M1 freeze achieved. Statement of work signed. Hardware security modules ordered against an 8–12 week lead time. |
| Phase 1 | Apr 2027 – Dec 2027 | Core build. Engine, contracts and compliance gateway reach first end-to-end issuance at M3. |
| Phase 2 | Jan 2028 – Jun 2028 | Integration and automated regression. Interoperability demonstrated at M4. |
| Phase 3 | H1 2028 | CRRC pilot data onboarded, or the synthetic fallback dataset substituted. |
| Phase 4 | Jul 2028 – Sep 2028 | Hardening. SLA validation and closure of the independent security and cryptographic audit. |
| Test cycle | Oct 2028 – Dec 2028 | System integration testing, user acceptance, pilot cycle, DORA resilience testing, go/no-go. |